Our structures sub's quote for the Route 788 bridge and the two retaining walls came in about $350K over our priced bid schedule. Can you tie their quote lines to our bid schedule lines and show me what's driving the difference? Attached are their quote, our priced schedule, the RFQ we sent them and the bar list.
Thinking…
Reinforcing steel explains $109,185, nearly a third. The barrier curb is priced twice, $59,470.
Quote vs. bid schedule