Can you write up our work plan and JHA on form WP-01 for the SR 389 culvert replacement at Kettle Grove Creek? Tie each special condition in the Corps' NWP 14 verification letter to the activity it applies to. I've attached the verification letter, the special provisions, profile Sheet C-302, the typical sections on Sheet C-501, Baseline Schedule Rev C and the staging and laydown plan. Flag anything in the documents that doesn't line up.
Thinking…
Culvert invert differs 0.50 ft between the profile and the typical section. 6 in-stream workdays fall after October 14.
Culvert work plan SR 389