We have Estimate Rev C for the PA 585 Clear Bend bypass earthwork and the 2027 earthwork schedule. Can you turn the estimate into a budget dashboard and build a week-by-week mass haul simulation for stockpile SP-1, so we can see whether it holds what the schedule sends it and what the double handling costs? I want to be able to change the C3 start, the number of haul trucks, loads per day and the stockpile area. The mass haul plan, the equipment plan and the geotech report for the E3 embankment are in the folder too.
Thinking…
SP-1 is over capacity for 10 weeks with C3 on schedule. 28% of the material is handled twice; the estimate carries 15%.
Mass haul simulation PA 585 Clear Bend