Examples Book demo

We closed out Walnut Row (job 24-061) in Lone Bend and I need a historical cost report for the estimating database. Can you take the final job cost detail, the sub final pay apps, the change order log and the buyout log and break the cost down by UniFormat II element, per GSF, per NRSF and per unit for each building, using the area takeoff and the unit mix schedule? Reconcile it to the estimate at award and show me where the variances actually sit.

Thinking…

Ask Yesper in a demo.

This is a finished result from Yesper. In a demo, Yesper works live and answers your questions.

Book a demo Contact us