Pre-bid cross-check, Lone Creek terminal lead and SR 536 crossing
Division 00–01, the Technical Specifications, the Bid Schedule, 38 plan sheets and the signal cable schedule were checked against each other. 32 discrepancies were found, 4 with a high impact on the bid price, and each one has a pre-bid question ready to send.
IFB No. LCPA 26-07, Lone Creek Port Authority, OhioUnit-price contract, track and crossing signal workTerminal lead Sta. 0+00 to 77+10, connection to the Lone Subdivision at MP 41.6Questions due Nov 16, 2026, 2:00 PMPrepared Nov 5, 2026
Summary
Quantity mismatch · Bid Schedule and cable schedule
The 19-conductor signal cable is 5,320 LF short in the Bid Schedule
Item 6.03 carries 4,070 LF of 19/C #14 AWG signal cable. The cable schedule (Rev 0) lists 14 cables of that type totaling 9,390 LF, 2.3 times as much. At our $11.00/LF the gap is $58,520, and every item is paid at plan quantity.
Ask which length governs and whether the item will be measured.
No pay item · specs, plans and Bid Schedule
The bungalow foundation is specified and detailed, but has no pay item
Sheet SG-21 details a 10 ft × 8 ft cast-in-place foundation under the crossing bungalow, and Specs Section 5.4.2 puts it in the Work. The Bid Schedule only has Item 5.12 to furnish and set the bungalow. Our estimate for the foundation is $24,500.
Ask for a pay item before carrying the cost in Item 5.12.
Count mismatch · three documents
Seven, six or five junction boxes, depending on the document
Signal Plan SG-11 and the cable schedule show JB-1 through JB-7. Specs Section 5.3.1 calls for six and Bid Schedule Item 5.08 for five. The two boxes beyond the Bid Schedule come to $23,000 at $11,500 each, including foundation and grounding.
Ask for the count and a revised quantity in Item 5.08.
Discrepancies between the documents
The matrix shows how many discrepancies there are between each pair of documents. Click a cell or filter by type and impact, then pick a discrepancy to see the excerpts from each document side by side. The Questions tab collects the questions into a memo, ready to copy.
0Discrepancies
0With a price impact
0Priced estimate impact
0Questions in the memo
Document against document
Discrepancies per pair of documents. Click to filter the list.
A discrepancy that involves three documents counts in all three pairs, so the matrix adds up to more than the number of discrepancies.
Filters
Type of discrepancy and impact on the bid price, based on our estimate.
Price impact
High$20,000 and upMedium$4,000 to $19,999Lowunder $4,000Noneclarification
Discrepancies
Questions
Sorted by impact on the bid price. Uncheck any question you do not want to send.
Memo to send
The text updates as questions are checked or unchecked.
Sources and method
Sources
IFB_LCPA-26-07_Div00-01.pdfInstructions to Bidders, Bid Form, General Conditions and Division 01 General Requirements, issued Oct 14, 202648 pages
Technical_Specifications_Track_Signal_Rev1.pdfTechnical Specifications for track, signal and conduit, Rev 196 pages
Bid_Schedule_Rev1.xlsxUnit-price Bid Schedule (schedule of items) with item descriptions and notes184 items
Signal_Cable_Schedule_Rev0.xlsxSignal and power cables with from–to, type, route and length52 cables
Method
Each document was broken into comparable entries: the Bid Schedule by item, the specifications by section, the plans by device and note, the cable schedule by cable and Division 00–01 by article and section.
Devices such as junction boxes, cables, handholes, foundations, gates and derails were matched across documents by tag and station.
Quantities were compared. Cable lengths were summed by cable type, ballast was computed as typical section × track length, and counts were taken from the plans.
Requirements in the specifications and Division 01 were compared with plan notes and Bid Schedule descriptions, and cross-references between documents were checked.
Each discrepancy was given a type, a price impact and a question worded for submission under Interpretations and Addenda in the Instructions to Bidders.
Assumptions and limitations
Estimate impact uses our own unit costs, for example $11.00/LF for 19/C #14 AWG signal cable, $11,500 per junction box and $52/ton for ballast. The figures show order of magnitude, not the Port’s estimate.
Impact: high from $20,000, medium $4,000 to $19,999 and low under $4,000. Four discrepancies cannot be priced until the Port answers (D09, D21, D24, D25) and are rated on their possible extent.
A discrepancy that involves three documents counts in all three document pairs in the matrix.
The review does not cover commercial terms such as liquidated damages, bonds and payment, or any assessment of claims after award.
The No. 10 lead length used to explain the 78 ft gap follows the common AREMA dimension. Some railroads’ own turnout standards differ slightly, so confirm it against the Port’s turnout standard drawing.