The duct schedule (kanalisation), the earthing list for the overhead contact line (KL) and the signal object and cable lists compared object by object along the chainage. The signal object list lacks a whole group of axle counter points, four cabinets are placed differently and pole references are shifted in three sections.
4 construction documents (bygghandling)Bandel 431 Nypvik–Sörmyra, km 12+000 to 21+00058 signal objects and cabinets, 151 KL polesPrepared 2026-11-05
Summary
Missing object group
12 axle counter points are missing from the signal object list
Between km 14+180 and 19+640 the objektlista (rev C) lists no räknepunkter (axle counter points). The kabellista has a cable to each of the 12 points and the kanalisation has a cable pit at each. On page 8, Rp 431-04 is followed directly by Rp 431-17.
Add the points to the objektlista, or confirm that they are to be removed from the other documents.
Cabinet positions
4 of 11 cabinets are placed differently
KS 431-07 is at km 17+150 in the kanalisation and jordningslista but at 17+390 in the signal documents, 240 m apart. KS 431-04 and KS 431-09 differ by 220 and 160 m, and KS 431-06 is on the other side of the track in the kanalisation.
Agree on one position per cabinet and update the documents that deviate.
Pole numbering
Pole references are shifted in 3 sections
20 of 93 references to KL poles point one or two poles further on than the jordningslista: the kanalisation at km 13+560–15+520 (+1) and 19+210–20+180 (+2), and the objektlista at km 16+600–17+560 (+1). Outside these sections the numbers match.
Confirm which pole numbering is current and renumber the references.
The four documents along the chainage
Each band is one document, drawn against the same km axis. An object that is in the same place in every document lines up vertically; a slanted connector or a hatched gap is a difference. Zoom in to see pole numbers and which pole each object refers to. Click an object, a pole or a difference for the source rows.
Highlight
Length shown
Position
0Signal objects and cabinets in view
0Same in every document
0With at least one difference
0Pole references shifted
KL poleCabinet (kopplingsskåp)Cable pit (kabelbrunn)SignalAxle counter point (räknepunkt)Balise groupPoint machineCablePosition or pole differsNot listedLeft side of the track above the line, right side below
Positions are drawn as given in each document. Pole connectors appear at 2 km and 500 m and run from each object to the pole number it refers to.
Differences
8 differences in 3 groups. Select one to zoom to it.
Selected
Source rows from each document.
Sources and method
Sources
Kanalisation_objektsförteckning_Bdl431_Nypvik-Sörmyra.xlsxDuct schedule: cable pits, cabinet foundations and track crossings, with side and nearest pole51 rows
KL_jordningslista_Bdl431_rev B.xlsxEarthing list for the overhead contact line: every pole with chainage, and cabinets and structures earthed to a pole163 rows
Signal_objektlista_Bdl431_rev C.pdfSignal object list: signals, point machines, axle counter points, balise groups and cabinets18 pages
Signal_kabellista_Bdl431_rev C.xlsxSignal cable list: from cabinet to object, with chainage at both ends and length45 cables
Method
Every row in the four documents was read into one list of objects, keyed on the object designation (for example Rp 431-06, KS 431-07). Cable pits in the kanalisation were matched to the object in their "Avser" column.
For each object type the documents where it should appear were set: cabinets in all four, signals, axle counter points and point machines in all but the jordningslista, controlled balise groups in the two signal documents.
Chainage and side were compared between documents. Any difference in chainage is reported.
Every pole reference in the kanalisation and objektlista was compared with the pole at that chainage in the jordningslista. Runs of references with the same offset are reported as one section.
Assumptions and limits
The jordningslista is taken as the reference for pole numbers and pole chainage, since it lists every pole.
Side is given as left (V) or right (H) in the direction of increasing km.
Only the four documents were compared. Drawings, the track layout plan and the cable route plan were not part of the check, so the review does not say which document is right.
Cable lengths in the kabellista, for example 495 m from KS 431-07 to Rp 431-10, were not checked against the axle counter's maximum cable length. That limit comes from the supplier's documentation and should be confirmed by the signalling designer.