Cost drivers
36% of the net sits in 25 items
The 25 largest items, 2.6% of the 974, add up to SEK 55.3 m. Half of the net sits in 47 items, while the 491 items below SEK 50,000 make up 8% together.
The net estimate for the track and platform rebuild at Tranängen, broken down into 974 items by work package, cost type, sub-area and price certainty. The net is unchanged at SEK 152.4 m, and 36% of it sits in 25 items.
Cost drivers
The 25 largest items, 2.6% of the 974, add up to SEK 55.3 m. Half of the net sits in 47 items, while the 491 items below SEK 50,000 make up 8% together.
Price certainty
SEK 25.4 m of the cost drivers rests on budget quotes (7 items, including the four EV-60E-760-1:15 switches and the contact line subcontract) or on the estimator's judgement (3 items: mast foundations, contaminated soil and platform shelters).
Request firm quotes for these before the tender is submitted.
Unit rates
Mast foundations work out at SEK 36,800 each against 20,600 in the resource bank (+79%). Ballast in sub-area 2 is +55%, platform edge installation +47% and the sub-base in sub-area 4 −46%.
Check the quantities and what each net line includes.
Each rectangle is one item, sized by amount and coloured by price certainty. Group by work package, cost type, sub-area or price certainty, click a group heading to open it and click an item to see its quantity, unit rate and basis. The Pareto curve shows how fast the net accumulates from the largest item down.
Faded items fall outside the current filter. Group areas follow the net estimate, so the treemap always adds up to SEK 152.4 m.
Items sorted from the largest amount down, cumulative share of the net.
| Rank | Item | Description (as in the estimate) | Package · area | Quantity | Unit rate (SEK) | Amount (SEK) | Price certainty | Flag |
|---|
| Work package | Net estimate rev B (SEK) | Sum of items (SEK) | Items | Difference (SEK) | Largest item |
|---|