Framing and drywall labor hours vs. schedule, Mill Bluff Apartments
The framing and drywall subcontractor's labor-hour budget is spread over master schedule Rev C level by level, showing where the framing front and the drywall front are each week and how many workers they need. From Level 4 up, the schedule drops the MEP rough-in week between the fronts, and at current crew sizes the last drywall is hung the week of Mar 1 instead of Feb 8.
Mill Bluff Apartments, SR 368, Mill Bluff, OhioLevels 1–6, 46 unitsLabor budget 4,154.0 hrsSchedule Rev C, weeks of Nov 9 – Feb 8Prepared Nov 5, 2026
Summary
Schedule logic
From Level 4 up, the rough-in week is gone
Levels 1–3 have one week for MEP in-wall rough-in and inspection between framing and drywall, as OAC meeting 7 requires (item 7.4). On Levels 4, 5 and 6, hanging starts in the rough-in week (Rev C, p. 2). In the week of Jan 4 the hang crew is also scheduled on Levels 3 and 4 at once.
Action: restore the rough-in week from Level 4 up and rerun the finish date.
Crew loading
Week of Jan 4 needs 13.7 workers; crews total 9
The drywall front has 390.2 budgeted hours on Levels 3 and 4 in one five-day week, which is 9.8 hangers against a crew of 5. The holiday weeks of Dec 21 and Dec 28 have 3 and 4 workdays and need 11.3 and 10.6 workers.
Forecast
At current crews, drywall finishes the week of Mar 1
With 4 framers, 5 hangers and one rough-in week per level, framing finishes the week of Feb 1 and drywall the week of Mar 1, three weeks behind schedule. More hangers alone won't recover it: with 4 framers the best case is the week of Feb 22. Getting back to Feb 8 takes 5 + 7 or 6 + 6.
The two fronts by level and week
The grid shows where framing, rough-in and drywall sit in schedule Rev C. The histogram below shows how many workers the budgeted hours need each week. Switch to the forecast to see where the fronts land at current crew sizes.
View
Rough-in per level (forecast)
Framing frontMEP rough-in and inspectionDrywall frontDrywall in the rough-in weekCrew size
Sources and method
Sources
Framing_Drywall_Labor_Budget_Rev1.xlsxMill Bluff Wall Systems LLC bid estimate: quantities, labor units and hours by level and line item, tabs "Framing" and "Hang", 8 hrs per day2 tabs
Master_Schedule_Rev_C_Interiors.pdfFraming, MEP rough-in and inspection, and drywall hang by level, weeks of Nov 9 – Dec 28 (p. 1) and Jan 4 – Mar 8 (p. 2), crew row and non-work days2 pages
OAC_Meeting_07_Minutes_2026-10-22.pdfItem 7.4: one week per level for in-wall rough-in and inspection before board4 pages
A-101_to_A-106_Floor_Plans.pdfUnit mix by level6 sheets
Method
Budget hours were read by level and line item: quantity × labor unit, summed into a framing total and a hang total per level.
The schedule bars for framing, MEP rough-in and inspection, and drywall hang were read level by level and week by week, together with the crew row (framing 4, hang 5) and the non-work days.
Each level's hours were spread over its scheduled weeks by workdays. Workers needed = hours ÷ (8 hrs × workdays).
Where hanging falls in the same week and on the same level as rough-in or framing, the cell is flagged against the requirement in the OAC minutes.
The forecast lets each crew work level by level at its size. Drywall can start a level once framing is complete and the rough-in time has passed.
Assumptions and limitations
Budget hours are used as actual hours, with no productivity factor or learning curve.
The labor units are the bid estimate's own. The board units (D-1 is 0.025 hrs per SF of wall, both sides) sit above common published labor references for single-layer board, which may be reasonable for small apartment rooms; an estimator should confirm them against current cost data.
5/8 in. Type X board on all partitions is the estimate's choice; codes require it only in rated assemblies. The day after Thanksgiving as a non-work day follows the schedule and depends on the labor agreement.
8 hours per workday per worker. No overtime or Saturday work.
Rough-in and inspection take one calendar week per level regardless of holidays.
No sick days, weather days or material delays. Drywall starts no earlier than the week of Nov 30, as scheduled.