Bid package review before advertisement, Heron Hills Town Center
The bid package for the Town Center streets, water main and new roundabout on SC 333 was reviewed before advertisement. It should not be advertised as is: 5 bid items have no governing specification, 7 referenced plan sheets are not in the package, and an internal reviewer note is still in the special provisions.
Bid package, 262 filesUnit price contract, SCDOT 2025 Standard SpecificationsOwner: Town of Heron HillsAdvertisement planned Nov 12, 2026Prepared Nov 5, 2026
Summary
Bid items vs. specifications
5 of 54 bid items have no governing specification
Every standard item maps to a section of the 2025 Standard Specifications, but 5 special items have no special provision. Item 8990124 Stamped Colored Concrete Truck Apron (410 SY, line 0460) is in the bid schedule, while the special provisions describe only a plain concrete truck apron (p. 58).
Action: add the provisions or revise the items before advertisement.
Plan sheet references
7 referenced plan sheets are not in the bid package
Four sheets are in the index of sheets but missing from the 254 sheet files. Three are in neither, including TC-14 Traffic Control Phase 3 for SC 333, which SP p. 14, the TC-01 general notes and IFB p. 17 all rely on.
Action: add the sheets or remove the references.
Leftover text
Internal reviewer note left on SP page 63
Light Pole Foundations still carries a QC note saying the foundation type may change and the package should be held. Sheet TC-01 cites the 2009 MUTCD, SP p. 44 cites the 2007 Standard Specifications, line 0200 carries a Spec Year 2007 pay item, and SP p. 31 has an unfilled section reference.
Action: settle the foundation type and delete the note.
Ready to advertise?
The status light sums up four checks. Click a check to see the documents behind it. Under Actions you can check off fixes and see how the status changes.
Do not advertise
View
Filter
No items match the search.
Filter
Sheet
Title
In index
File
Refs
Status
No sheets match the search.
Sources and method
Sources
IFB_Heron_Hills_Town_Center.pdfInvitation for Bids, Instructions to Bidders, Bid Form and list of bid documents38 pages
Project_Special_Provisions.pdfProject special provisions supplementing the SCDOT 2025 Standard Specifications124 pages
Bid_Schedule_Heron_Hills_Town_Center.xlsxBid schedule with SCDOT pay item numbers54 items
Sheet_Index_Heron_Hills_Town_Center.pdfIndex of sheets from the title sheet258 sheets
Plan_Set_Heron_Hills_Town_Center.zipPlan sheets as PDF, one file per sheet254 files
Geotechnical_Report_SC333_Roundabout.pdf, Drainage_Report_Town_Center.pdf and two other attachmentsReference documents attached to the bid package4 files
Method
All 262 files were read. Bid items were taken from the bid schedule, and provision titles and page numbers from the special provisions.
Each bid item was matched to its governing document. A standard SCDOT pay item counts as covered by the Standard Specifications section given by the first three digits of its number. A special item (899 series) needs a project special provision. Provisions with no bid item were listed as well.
Every sheet number mentioned in the IFB, the special provisions and on the plan sheets was collected and compared with the index of sheets and the files in the plan set.
The IFB, special provisions and plan notes were searched for reviewer notes, initials with dates, placeholders such as X.X, and references to superseded editions of the Standard Specifications, the MUTCD and the pay item list.
Each finding was linked to an action. The status light stays red while any finding leaves bidders without a basis for pricing, and turns amber when only editorial corrections remain.
Assumptions and limitations
Standard pay item numbers were checked against the section numbering only. Each item should be confirmed against the SCDOT Specification Year 2025 pay item list before advertisement.
Sheet content was not reviewed, only that each sheet exists and its number matches. Revisions were not compared.
Coordinates (NAD83(2011) South Carolina State Plane, international feet) and elevations (NAVD 88) were not checked.
Supplemental Specifications and Supplemental Technical Specifications in effect for the letting were not reviewed against the provisions.