Bid go/no-go: track surfacing and ballast, Pine Subdivision and connecting lines
Bid decision for the Quillan Gap Rail Authority's 2027 surfacing and ballast program around Pine Crossing, PA. The recommendation is to keep pricing the job, but two issues decide it: the experience requirement in the bidder qualifications and the ballast quantity in the bid schedule. Both need answers before questions close on Nov 17.
IFB QGRA-26-014 dated Oct 28, 2026, six documentsPine Sub and three connecting lines, 18.7 track miles, 14 turnoutsBids due Dec 1, 2026, 2:00 PMPrepared Nov 5, 2026
Summary
Qualification · Instructions to Bidders
Experience requirement not met for 2025 on own contracts
Bidders must show at least 75 track miles of production surfacing in each of 2023 through 2025 on projects where they were the contractor (Instructions to Bidders, p. 9). Own contracts gave 65 track miles in 2025; adding 14 track miles as a subcontractor brings it to 79. Ask whether subcontract work counts, and line up a named surfacing subcontractor in parallel.
Quantity · Bid Schedule Item 5
Ballast quantity leaves out Main 2 on the Laurel Fork Sub
The bid schedule carries 5,800 tons of ballast. The spec rate of 400 tons per track mile over the 18.7 track miles in Attachment B gives 7,480 tons, 1,680 tons more (+29%). Item 5 is a plan-quantity item (Special Provisions, p. 17), so the $107,520 difference is ours unless it is priced.
Risk matrix · 15 risks
The four highest risks are all project-specific
General risks score 9 of 25 at most and are covered by the standard markup. Six project-specific risks beyond the two decisive issues add up to $103,000, 9.8% of the estimate.
Bid decision worksheet
Pick an answer to each decisive issue to see how the recommendation and the estimate change. Open a requirement to read the source text, or click a risk in the matrix for its rating, response and contingency.
Recommendation
Estimate before contingency
Unpriced quantity risk
Project-specific contingency
Until questions close on Nov 17
Decisive issue 1 · Qualification
Experience gate: 75 track miles of surfacing per year, 2023–2025
Decisive issue 2 · Quantity
Conflicting ballast quantity: bid schedule vs. specifications
Requirements by area
Status against our own capacity and the bid documents. Requirements tied to a decisive issue change with the answers above.
The bid schedule and the specifications work from different track lengths. Attachment B shows the difference is Main 2 on the two-main-track Laurel Fork Sub.
Segments in Attachment B
Ballast per segment at the spec rate of 400 tons per track mile.
Line
Limits
Track
Length (mi)
Ballast at spec rate (tons)
In bid schedule
Estimate by bid item
Our unit prices as of October 2026. Only Item 5 differs between the bid schedule and the spec rate.
Item
Description
Unit
Bid qty
Qty at spec rate
Unit price ($)
Amount at bid qty ($)
Difference ($)
Sources and method
Sources
QGRA-26-014_Instructions_to_Bidders.pdfBid procedures, bidder qualifications, bonds and question deadline22 pages
QGRA-26-014_Technical_Specifications_Track_Surfacing.pdfSurfacing method, ballast rate, tolerances and geometry testing24 pages
QGRA-26-014_Bid_Schedule.xlsxBid items with quantities and units8 items
Attachment_B_Work_Limits_and_Segments.xlsxSurfacing limits by line and track, turnouts6 segments, 14 turnouts
Attachment_D_Work_Windows_and_Haul_Routes.pdfTrack work windows by line and truck haul routes9 pages
Attachment_F_Environmental_Commitments.pdfWellhead protection, noise limits and engine requirements14 pages
Surfacing_Production_Log_2023-2025.xlsxOur production by contract, as contractor and as subcontractor41 contracts
Method
Read the Instructions to Bidders, Special Provisions, Technical Specifications, bid schedule and attachments, and sorted every requirement into five areas: contract terms, technical, environment and community, bidder qualifications and schedule.
Rated each requirement against our own fleet, staff and production log as Met, Watch or Decisive.
Recomputed the bid schedule quantities from the spec ballast rate and the Attachment B segments, segment by segment.
Rated each risk for likelihood and impact from 1 to 5 and split the risks into project-specific ones, which come from these bid documents, and general ones, which come with any surfacing job.
Priced the project-specific risks as their own contingency. General risks sit in the standard markup and are not priced one by one.
Assumptions and limitations
The estimate is preliminary and uses our unit prices as of October 2026.
The 1,680-ton difference is priced at the same unit price, $64.00 per ton, including the extra ballast train trips.